RIO DE JANEIRO, Dec. 29 (Xinhua) -- Construction work at Rio de Janeiro's Barra Olympic Park, the main venue cluster for next year's Olympic Games, has reached 95% completion, organizers said on Tuesday.
The complex will comprise nine venues that will host 16 Olympic and nine Paralympic events, in addition to the main press center and international broadcast center.
Meanwhile the Olympic and Paralympic Village, which will host nearly 14,000 athletes next year, is 97% ready according to Rio2016.com.
The Olympic Hockey Centre is 99% complete and the Youth Arena (for basketball, modern pentathlon and wheelchair fencing) 75% finished.
Work on the golf course and three X-Park facilities has already been completed.
The least advanced venues are the Youth Arena, which will host basketball and fencing (75%) and the velodrome (76%).
- 英语文摘:Chelsea, Leicester draw, Everton-Man City postponed due to COVID-19
- 英语文摘:CBA roundup: Shanghai snaps Guangdong's 9-game winning streak, Fujian smashes Nanjing
- 英语文摘:Messi grateful for Ballon d'Or Dream Team spot
- 英语文摘:New York nurse receives COVID-19 vaccine, kicking off state inoculation
- 英语文摘:Flick's lucky hand: Paris pupil Coman securing Bayern's glory